Eight Companies, 7,116 Jobs, 730 Acres: What Brownsville's Economic Report Promised, and What the Records Show Arrived

2 days ago
9 min read

BROWNSVILLE, Texas. The Greater Brownsville EDC published its Fiscal Year 2025 Annual Impact Report in February. It listed eight companies attracted, $183.7 million in investment, 3,288 jobs created and 7,116 more jobs committed for 2026. It put 730 acres of industrial land on the cover.


Nine months have passed. That is enough time to check.


The 956 Report went through the report line by line and matched each claim against public documents. State construction registrations. Company releases. Board agendas. Federal job counts. Census files.


The result: two of the eight companies have publicly documented openings. One more had a completion date that has passed with no public confirmation. Three cannot be traced to any public project record. The job numbers do not appear in the federal count. And the industrial park that was set for an August grand opening has no public record of one.


None of that proves a project failed. It shows what the public can and cannot verify about an agency funded by a quarter-cent of the city's sales tax.


The Eight Companies

Page 5 of the report lists them. Amazon. CIL Development. Grupo Ayusa. Linde. Luceca LLC. RVO Real Estate Holdings Inc. Superior GHQ. Ziwa Corp.


Page 5 panel from the GBEDC FY 2025 Annual Impact Report showing a 20-to-1 capital investment leverage claim, $183.7 million in investment attraction, a 730-acre industrial site and a 98-acre Phase 1 site under development, and a numbered list of eight companies attracted: Amazon, CIL Development, Grupo Ayusa, Linde, Luceca LLC, RVO Real Estate Holdings Inc., Superior GHQ and Ziwa Corp.
Page 5 of the report lists the eight companies GBEDC says it attracted in fiscal year 2025. Image: Greater Brownsville Incentives Corp./GBEDC FY 2025 Annual Impact Report

Amazon: Delivered

Amazon announced a 62,000-square-foot delivery station at 1910 FM 511 on May 14, 2025. KRGV reported it opened on March 20, 2026. Amazon has not published a job count for the Brownsville site. The company says the 13 delivery stations it has opened outside major Texas metro areas each create an average of 170 jobs at the station itself.


Linde: Started up, according to the company

This is the big one. Linde's air separation plant was announced at about $100 million. That is roughly 54 percent of the report's entire investment total. It was projected to bring 90 to 100 jobs, according to ConstructConnect, and was supported by $1.3 million in job training incentives and grants, according to Area Development. Linde's own release said the plant was expected to start up in the first quarter of 2026. The City of Brownsville said it would be fully operational by spring 2026.


On Linde's Feb. 5, 2026, earnings call, CEO Sanjiv Lamba told investors the company started up a plant in Brownsville in early January. Morningstar also reported in June that Linde started the Brownsville unit in the first quarter of 2026. As of Nov. 25, The 956 Report found no published count of how many jobs the plant has filled.


Superior GHQ: Scheduled, not publicly confirmed

The metal fabricator broke ground on a 15,000-square-foot building in August 2025. GBEDC described a $3 million to $4 million investment and 15 to 20 first-year jobs. The state registration for the project lists an estimated construction cost of $800,000 and a completion date of Aug. 1, 2026. State figures cover construction only. No opening announcement was found.


Grupo Ayusa: Built, but was it attracted?

Grupo Ayusa describes itself as a construction and leasing company and lists a Brownsville office. State records show its $7 million warehouse on Industrial Circle was registered on Feb. 15, 2024, with work starting that month and a target completion of Feb. 28, 2025. The project began more than seven months before the fiscal year the report covers.


Luceca: A warehouse registration

State records list a Luceca warehouse on G.B.I.C. Circle, owned by Luceca Holdings LLC, at an estimated $1.1 million, registered in April 2025 with a target completion of April 30, 2026.


CIL Development, RVO Real Estate Holdings Inc., Ziwa Corp.: Not traceable

No public announcement, state registration or news report could be matched to these three names as they appear in the report.


The Jobs

The report says 3,288 jobs were created in 2025.


Page 6 panel from the GBEDC FY 2025 Annual Impact Report naming Linde as top business investment, a bar chart of investment by target industry, and the figures 10,604 jobs retained in 2024 to 2025, 3,288 jobs created in 2025 and 7,116 jobs committed to add in 2026, with Bechtel named top leading employer.
The report's job figures on page 6. The report names no employers behind the 3,288 or 7,116 figures. Image: Greater Brownsville Incentives Corp./GBEDC FY 2025 Annual Impact Report

The Bureau of Labor Statistics counted 159,200 payroll jobs in the Brownsville-Harlingen metro in September 2025. BLS lists that as down 1.8 percent from a year earlier. That works out to roughly 3,000 fewer jobs across the report's own fiscal year, from 162,200 in September 2024. The annual averages agree: 162,100 jobs in 2024 and 160,300 in 2025.


The Dallas Fed reported that Brownsville's unemployment rate rose 1.9 percentage points from the start of 2025 through August and moved above McAllen's for the first time in more than a decade.


The report says employers committed to add 7,116 jobs in 2026.


BLS now counts 158,700 jobs in the metro for September 2026, down 500 from a year earlier. When BLS first published the September figure, it said the over-the-year change was not statistically significant. Preliminary October data shows 159,700 jobs, down 300 from October 2025. The Dallas Fed reported Brownsville employment fell at a 2.8 percent annualized rate from June through September.


Individual employers can hire while a metro shrinks. But the report names no employers for either figure. The public jobs tied to the eight companies add up to a fraction of the claim: 90 to 100 at Linde, 15 to 20 at Superior GHQ, and an unstated number at Amazon.


The report names Bechtel as the top leading employer. Bechtel is building the Rio Grande LNG terminal, where the company says the construction workforce will reach about 5,000 at peak. The report does not say whether temporary construction jobs are in its totals.


The 730 Acres

The cover says 730 acres under development. Here is what the record shows on the ground.


Cover of the Greater Brownsville EDC Annual Impact Report FY 2025, with a photo of a Starship rocket beside its launch tower and the figures $183.7 million investment attraction, 730 acres industrial site under development and 25 businesses retained.
The report's cover puts 730 acres under development. Image: Greater Brownsville Incentives Corp./GBEDC FY 2025 Annual Impact Report. The cover photo is credited in the report to SpaceX (via X).

May 2025. GBEDC breaks ground. The Brownsville Herald reports a first phase of 86 acres and 13 plots, expected to take 16 months. That schedule pointed to September 2026.


February 2026. The annual report lists Phase 1 at 98 acres.


March 2026. In his State of the City address, Mayor John Cowen Jr. says the 730-acre district has 24 lots, 19 of them under letters of intent. A video shown during the address features City Commissioner Tino Villarreal Jr. calling it a $500 million project with a first phase of 86 acres and 13 plots.


June 2026. CEO Gilberto Salinas tells KURV radio the park is 750 acres with a 100-acre first phase of 13 lots, the Rio Grande Guardian reports. He says nearly all are spoken for under letters of intent, that title work is wrapping up, and that a grand opening is set for August. He says dirt is moving on Phase 2.


August 2026. The GBEDC board agenda lists five bids for an "Industrial Subdivision Development Project, Phase 2." The low bid was $16,281,006.56 from Cornett Construction Co. The agenda item was to award the contract at that price and let the CEO approve change orders of up to $50,000 each. The agenda does not use the Tech District name.


October 2026. Salinas describes a 740-acre park that is "nearing completion," with three active prospects lined up, the Rio Grande Guardian reports. One, which the article describes as a $300 million to $400 million investment from a SpaceX supplier, is expected to be announced after the park is completed at year's end.


Three aerial photos from page 6 of the GBEDC FY 2025 Annual Impact Report showing the Tech District site as open farmland in September 2024, graded land in February 2025, and new roads and cleared lots labeled Phase 1 development December 2025.
The report's aerial photos of the Tech District site, labeled September 2024, February 2025 and Phase 1 development December 2025. Image: Greater Brownsville Incentives Corp./GBEDC FY 2025 Annual Impact Report

As of Nov. 25, The 956 Report found no public record of the Phase 1 grand opening. It read the nine GBEDC board agendas posted from April through November 2026. None lists the sale of a lot. A letter of intent is not a sale.


Three acreage figures for the whole park. Three for the first phase. Two lot counts. One construction contract of $16.3 million for the second phase before a public record shows a buyer closing in the first.


What the Board Agendas Show

The 956 Report read all nine GBEDC agendas posted from April through November 2026. They are the paper trail of what the board was actually asked to act on. In open session, the board was asked to consider:


April 16. A contract with Development Counsellors International, described as a New York-based firm for marketing, public relations and site-selector outreach. No dollar amount is listed.


July 6. Two agreements with the Brownsville Public Utilities Board for wastewater treatment capacity and water supply. A BPUB payment for water rights of $176,091.30. A City of Brownsville parkland fee of $201,900. An "Office Building."


July 16. A first payment of $210,000 under a performance agreement for Rich Products. Rich Products is not among the eight companies the annual report lists as attracted.


Aug. 20. The $16.3 million Phase 2 construction contract. Adoption of the Fiscal Year 2027 budget.


Sept. 24. Approval of a strategic plan.


Oct. 15. An agreement among the city, Cameron County and GBEDC for Tax Increment Reinvestment Zone Number Five.


Nov. 19. The $1,000,000 first payment to SpaceX.


Not one of the eight companies from the annual report appears by name on any of those agendas. Neither does a lot sale or a grand opening.


What does appear is a growing list of code names in closed session. Project Industrial. Project Hot Rod. Project Nosewheel. Project Train. Project Life. Project Red Chair. Project Western Boots. Project PLR. Project Assemble. Project Proximus. Project Chiquita. Project Big Tuna. Twelve names since April. The agendas do not say what any of them are.


An agenda shows what a board was asked to consider. It does not show how the board voted.


What the $9.24 Million Bought

The report says GBEDC spent $9.24 million. Its web version gives some results.


Page 8 panel from the GBEDC FY 2025 Annual Impact Report showing 11 staff members, $9.24 million in actual expenditures, a 20-to-1 leverage claim, a pie chart of community support by category, $111,000 in community support to 27 organizations, $621,000 invested in workforce programs at nine organizations, 86 business engagements and two performance agreements.
Page 8 of the report: $9.24 million in spending and two performance agreements, with no companies named. Image: Greater Brownsville Incentives Corp./GBEDC FY 2025 Annual Impact Report

$621,435 went to workforce programs at nine organizations, reaching 481 people. That is about $1,292 per person. GBEDC's partners reported 82 employees upskilled through TSTC, 76 residents given training scholarships through BISD, and 109 participants through VIDA.


$110,970 went to 27 community organizations.


GBEDC also pays toward debt on the Brownsville airport terminal. The web version puts that at $6,608,000 from 2019 through 2025.


The rest is not itemized. The report shows two performance agreements for the year and does not name the companies. State law requires those agreements to spell out job and investment targets and what must be repaid if they are missed.


The Pipeline

The chairman's letter said other prospects were in the pipeline. In June, Salinas put numbers on it: five major announcements, about $2 billion in investment and 2,500 to 3,000 primary jobs, all to be wrapped up before the end of the year.


One announcement of that scale has been made in public since. Saronic Technologies announced its Port Alpha shipyard on July 16. The governor's office put it at $3.248 billion and 10,000 jobs, with an $80 million state grant. Ground was broken Sept. 30, and the first phase is expected to be operational by 2028. KRGV reported a 95 percent county tax break. The Texas Tribune reported GBEDC is offering another $10 million. The June interview mentions Saronic's proposed shipyard separately and does not say whether it was one of the five.


Five weeks remain in the year.


The SpaceX item stands out. GBEDC's Nov. 19 consent agenda listed approval of a first payment to SpaceX of $1,000,000 as an economic development incentive payment under an agreement between the two. The agenda does not describe what SpaceX must deliver.


The Population Claim

The report cites a rising population. The Census Bureau's 2025 estimate for Cameron County is 433,946, up 994 in a year. Births over deaths added 2,610. International migration added 204. Domestic migration subtracted 1,837. More people moved out to other parts of the country than moved in, as in every year since 2020.


The Scorecard

  • Publicly documented as open or operating: Amazon (opened March 20, 2026); Linde (started up in early January 2026, according to its CEO).

  • Completion date passed, no public confirmation: Superior GHQ.

  • Building registered, begun before the fiscal year: Grupo Ayusa.

  • Warehouse registration only: Luceca.

  • No public record found: CIL Development, RVO Real Estate Holdings, Ziwa Corp.

  • Jobs created, 3,288: not reflected in federal data.

  • Jobs committed for 2026, 7,116: not reflected in federal data through September.

  • Tech District Phase 1: no public record of a grand opening or a closed sale.

  • Tech District Phase 2: a $16.3 million construction contract on the August agenda.

  • Incentive payments on 2026 agendas: $210,000 for Rich Products, $1,000,000 for SpaceX.

  • Five announcements by year's end: one of that scale made public.


The Questions That Remain

How many people work at the Linde plant?


Has a single lot in the Tech District been sold?


Who are the employers behind 7,116 jobs?


Which two companies signed performance agreements, and has either met its targets?


What does SpaceX owe Brownsville for $1,000,000?


Every one of those answers sits in a record GBEDC holds. The 956 Report has published the annual report and the source records alongside this story, listed below.


What we could not confirm

  • Whether Superior GHQ's Brownsville facility is open, and how many people work there.

  • Whether CIL Development, RVO Real Estate Holdings Inc. and Ziwa Corp. have projects in Brownsville. No public record was matched to those names. That does not mean the projects are not real.

  • How many jobs Linde and Amazon have filled in Brownsville.

  • How the GBEDC board voted on the agenda items above. Agendas show what the board was asked to consider; minutes for these meetings were not reviewed.