Harlingen Data Center Ordinance Is Recommended 4-1, According to Video Posted by Harlingen Insight

4 days ago
7 min read
On-screen graphic from video posted by Harlingen Insight reading "COMMISSION VOTES IN FAVOR 4-1," over a view of the dais at Harlingen City Hall.
Video posted by Harlingen Insight, labeled as the Nov. 23, 2026, Planning and Zoning Commission meeting. The 4-1 vote has not been confirmed in official city minutes or in an official city meeting video.

HARLINGEN, Texas - A Harlingen data center ordinance was recommended to the City Commission on a 4-1 vote, according to video of the meeting posted by Harlingen Insight, which includes an on-screen graphic that reads, "COMMISSION VOTES IN FAVOR 4-1." The official city video and minutes of the Monday, Nov. 23, Planning and Zoning Commission hearing had not been posted as of late Monday night, and The 956 Report has not independently confirmed the vote.


The draft in the commission's packet would allow high-intensity data centers of 25 megawatts or more only in the Heavy Industry district, only inside a new overlay, and only with a Special Use Permit approved by the City Commission. It does not cap how many of those facilities the city may approve.


The hearing was held during Thanksgiving week, at 5:30 p.m. in City Hall Town Hall, 118 E. Tyler Ave. In the video posted by Harlingen Insight, a speaker who is not named called for a ban on data centers in the city and said residents had asked for studies they have not received. The City Commission is scheduled to hold a public hearing on the ordinance Wednesday, Dec. 2, at 5:30 p.m. at the same location.


WHAT THE HARLINGEN DATA CENTER ORDINANCE WOULD DO

The packet marks the ordinance as a draft. Planning and Development Director Ana Hernandez, AICP, wrote that staff "recommends approval of the draft ordinance subject to recommended changes." The 956 Report could not confirm from the Insight video whether the commission recommended the draft as written or with changes.


Under the draft, a high-intensity data center is a facility or campus with a connected electrical load of 25 megawatts or more at full build-out. The use would not be allowed by right in any zoning district. Each project would need Heavy Industry zoning, its own overlay district, and a Special Use Permit approved by the City Commission after public hearings. The usual option of approving a special use permit without a hearing when no written complaint is filed would not apply.


The draft sets no limit on the number of facilities or on total megawatts. Each project would still need its own zoning, overlay and permit votes, and mailed notice to property owners within 500 feet at least 15 days before the City Commission hearing.


Applicants would have to file engineer-sealed studies covering water (average and peak demand, including drought), wastewater, electricity, drainage, traffic, cooling technology, noise, lighting, airport impacts and decommissioning. The City Engineer and Harlingen Waterworks System would review them, and the city could hire third-party reviewers at the applicant's expense.


Other standards in the draft include:


  • No potable water for cooling unless the permit expressly allows it. In a drought, backup potable use would be cut before residential customers are affected.

  • Noise limits of 55 dBA from 10 p.m. to 7 a.m. and 60 dBA at other times, measured at the nearest home, school or other sensitive use, with follow-up testing after opening and annually for five years.

  • A 50-foot setback from property lines, and a 500-foot separation for buildings, cooling equipment, generators and bulk fuel storage from residential zoning and from homes, schools, child care, hospitals, nursing homes, churches and parks. A 50-foot landscaped buffer and a 6-foot opaque wall would be required next to residential areas.

  • A decommissioning plan with financial assurance, annual public compliance reports, and a ban on agreements that keep the applicant's identity or scale confidential.


A permit would lapse if no building permit is issued within two years, or if operations stop for 12 months.


WHAT WAS SAID AT THE HEARING

The 2-minute, 34-second video posted by Harlingen Insight is labeled as a Planning and Zoning Commission meeting. It shows one speaker at the podium. The video does not identify her by name, so The 956 Report is not naming her.


"And now you're bringing this hearing the week of Thanksgiving," she said. "Let me be clear, we do not want another data center in Harlingen, not outside our city limits, not inside our city limits."


She said residents had "requested studies, engineering reports, drainage assessments, environmental information, utility impact reports, and documentation explaining what these projects will mean for our community," and that they had "received nothing." She asked what happened to the studies from the city's data center moratorium, and she listed water-use projections, electrical infrastructure assessments, drainage and flood studies, environmental assessments, an energy response plan, and a cumulative impact assessment.


"The only ordinance we want to see is one banning data centers within the city limits," she said. "San Marcos did it and no one sued them." She closed, "No rezoning, no permits, no data centers, ever."


The 956 Report confirmed that the San Marcos City Council voted 4-3 on June 16, 2026, to ban data centers in every zoning district. It has not confirmed whether anyone sued the city over that ban.


A woman with red hair speaks at a microphone in a meeting room, with an on-screen graphic reading "COMMISSION MEETING," in video posted by Harlingen Insight.
A speaker, who is not named in the video, addresses the Nov. 23 hearing in video posted by Harlingen Insight.

The clip does not show members raising their hands or a roll call. The 4-1 tally appears only as text added to the video. The footage also does not include a statement from the city attorney. The official city meeting video had not been posted as of late Monday night.


THE MORATORIUM AND THE MISSING STUDY

The City Commission approved a 120-day moratorium on high-intensity data center applications, Ordinance No. 26-26, on June 17, 2026, after a first reading on May 20. The signed ordinance says it was "intended solely to allow the City to complete a focused planning and regulatory process" and "is not adopted to prohibit" data centers. The city later extended the moratorium in August 2026. The 956 Report has not confirmed the extension's second-reading date or its exact expiration date.


The moratorium authorized planning work on water supply, coordinated with Harlingen Waterworks System; wastewater; electric-utility coordination; land-use and noise compatibility; and proposed zoning standards. On May 20, Commissioner Daniel Lopez also asked for an environmental impact study, according to MyRGV.


The draft Harlingen data center ordinance recitals cite a city-commissioned report, Ambiotec Civil Engineering Group Inc.'s "High Intensity Data Center Impact Evaluation and Planning Standards Study (October 2026)." According to those recitals, the study looked at water, wastewater, electrical, noise, air, heat, lighting, traffic, drainage and airport impacts, and it recommended that the use not be allowed by right, that it be defined by electrical load, and that each phase be approved only after water, wastewater and electric capacity are verified.


The study itself is not in the Nov. 23 Planning and Zoning packet, which mentions it only in the staff summary and the recitals. The 956 Report could not find a public copy on the city's website or in news coverage. Under the draft, project-specific impact studies would be required from each applicant, not from the city.


PROJECTS NEAR HARLINGEN, OUTSIDE THE CITY

Two large proposals have been reported in unincorporated Cameron County, outside Harlingen city limits, near Valley International Airport. Fluidstack has described a first phase of about $4 billion on more than 1,100 acres east of the airport; Cameron County issued a worksite permit on Sept. 10, 2026, and the company has said construction has begun. Eneus Energy has described an "RGV Data Center" of up to 2 gigawatts on about 1,785 acres. In 2025, the Harlingen Waterworks System board approved an agreement to supply up to about 4.6 million gallons a day of treated effluent for that project, according to later news coverage. Neither project is inside the city, and The 956 Report could not confirm that either is operating. In August 2026, KRGV reported that the city said there were no data center proposals within city limits.


WHAT TO WATCH

The Planning and Zoning recommendation, if confirmed in official minutes, does not adopt the ordinance. Only the City Commission can do that.


The next public hearing is Wednesday, Dec. 2, at 5:30 p.m. at City Hall Town Hall. A City Commission workshop is scheduled for Tuesday, Dec. 8, at 5:30 p.m. at the same location; the packet says no formal action will be taken at the workshop. The draft leaves the dates of first and second readings blank.


Residents can also watch for official minutes or an official city video of the Nov. 23 hearing, which would confirm the 4-1 tally, who voted no, and whether any changes were attached to the recommendation, and for any public release of the October 2026 Ambiotec study.


NEXT MEETING: WHAT'S ON THE AGENDA

The Harlingen City Commission is scheduled to meet Wednesday, Dec. 2, 2026, at 5:30 p.m. at City Hall Town Hall, 118 E. Tyler Ave. A public hearing on the proposed high-intensity data center amendments to Chapter 111 is set for that meeting, according to a public hearing notice published Nov. 7 and later reporting by the Harlingen Post. Agenda items can change. The city's meetings portal is at harlingentx.portal.civicclerk.com.


WHAT WE COULDN'T CONFIRM

  • The official 4-1 vote, who voted no, and whether the commission recommended the draft as written or with changes. The tally appears only as text added to video posted by Harlingen Insight. It has not been confirmed in official minutes or in an official city meeting video, which had not been posted as of late Monday, Nov. 23.

  • The speaker's name. It does not appear in the video.

  • Any remark by the city attorney at the Nov. 23 hearing. The video posted by Harlingen Insight does not include one, and The 956 Report has not confirmed such a statement from an official record.

  • Whether every shot in the Insight video is from the Planning and Zoning hearing itself. The video is labeled as that meeting. Some dais nameplates were not clearly readable.

  • Whether the October 2026 Ambiotec study has been released to the public.

  • The moratorium extension's second-reading date, ordinance number and exact expiration date.

  • The current status of the Fluidstack stormwater agreement with the city, and whether Eneus has filed a formal application.

  • Whether anyone sued San Marcos over its June 2026 data center ban.


SOURCES

Video of the meeting posted by Harlingen Insight, Nov. 23, 2026.


City of Harlingen, Planning and Zoning Commission agenda, Nov. 23, 2026.


City of Harlingen, Planning and Zoning Commission packet, Nov. 23, 2026, including the draft Chapter 111 amendments and staff summary.


City of Harlingen meetings portal, Planning and Zoning Commission, Nov. 23, 2026 (CivicClerk event 1758).


City of Harlingen, Ordinance No. 26-26, approved June 17, 2026.


Public hearing notice, high-intensity data center ordinance, City of Harlingen, published Nov. 7, 2026.


Harlingen Post, "Harlingen weighs data center zoning restrictions Nov. 23," Nov. 18, 2026.


MyRGV, "Harlingen sets moratorium as two data centers show interest in county," May 21, 2026.


MyRGV / Valley Morning Star, "Harlingen extending data center moratorium," Aug. 20, 2026.


Cameron County, "Worksite permit issued for Fluidstack data center project," Sept. 10, 2026.