Boeye Reservoir McAllen: The City Set Aside $21 Million. Here Is Where It Went.
$21 million.
That is what McAllen moved out of its General Fund and into a fund for the Boeye Reservoir project, according to the city's own budget documents.
About $7.9 million of it has gone to the reservoir site over the last three fiscal years, counting one year of city estimates.
$7.5 million paid a court award for park land in north McAllen.
$6.56 million is headed to Quinta Mazatlán.
And the Boeye line in the city's fiscal year 2026-27 budget is zero.

All of this happened while the city was promoting a $230 million luxury district on the site and collecting proposals from developers. Thirteen months after that announcement, a search of city postings and local news coverage turns up no public announcement of a master developer as of Nov. 27, 2026.
City records list the Boeye Reservoir McAllen site at 1901 South 23rd Street. Here is what the records show, and what they do not.
What the city promised
On Oct. 14, 2025, McAllen leaders held a press conference at the McAllen Performing Arts Center. The theme was "New Grounds, New Heights."

"This project is, I think, one of the biggest projects the city has ever done," Mayor Javier Villalobos said, the RGV Business Journal reported. City officials described a full-service luxury hotel, an artisan village with local retail and fine dining, and a recreation district anchored by "a sterling waterfront." The 70-acre site sits south of Interstate 2 between Bicentennial Boulevard and 23rd Street, as the Progress Times has described it.
The city's projections, as reported by the RGV Business Journal: 460,000 visitors a year, about $35.6 million in annual visitor spending, almost 900 permanent jobs, at least 2,200 jobs supported during construction and $330 million in total economic output from construction.
The headline number was a $230 million investment. The Rio Grande Guardian reported the city was seeking a public-private partnership. The coverage does not spell out how much of the $230 million would be public money and how much would be private.
City Manager Isaac "Ike" Tawil told The Monitor in November 2025 that the city did not yet know how much it would spend, because no final design had been chosen. By January 2026, city leaders put the project's possible cost at $200 million to $400 million, ValleyCentral reported.
Even the concept was not consistent that week. Several outlets described a water attraction. ValleyCentral reported that Villalobos said the city was moving away from a previously planned recreational area with water features. "We're going a different route," he told the station.
What the city set aside
The General Fund pages of the city's fiscal year 2024-25 budget book show a $21,000,000 "Transfer to City Hall Expansion Fund" as an actual transaction in fiscal year 2022-23.
The fiscal year 2023-24 budget book says the City Hall Expansion / Reservoir Development Fund exists to pay for City Hall expansion and development of the reservoir. It also says $21.2 million had been budgeted for the reservoir development project.
The fiscal year 2024-25 budget described the plan in detail. Reservoir Development, 1901 South 23rd Street, $21.6 million:
$295,000 for a feasibility study.
$7 million for Phase 0, grading.
$14.3 million for Phase 1, platting and infrastructure.
The city's annual financial report for the year ending Sept. 30, 2025 repeats those figures. It says platting and infrastructure were scheduled for completion in September 2026. The report for the year before had put that date at December 2025.
What the city spent on Boeye

Fiscal year 2023-24. The city budgeted $21,175,377 for the reservoir. It spent $2,104,345, according to the city's annual financial report for that year.
Fiscal year 2024-25. The city budgeted $19,070,377. It spent $4,847,597. That left $14,222,780 of that year's budget unspent, according to the budget-to-actual schedule in the annual financial report.
Fiscal year 2025-26. The city started the year with $16,000,000 budgeted for reservoir development. A November budget amendment, described below, cut that line to $8,500,000. The city's own estimate of what it spent: $922,712.
Add the three and the reservoir line comes to about $7.87 million across three fiscal years. Two of those figures are audited actuals. The third is a city estimate. The records reviewed do not break that spending down by vendor or task.
A second pot also paid for Boeye. The Tax Increment Reinvestment Zone 2A fund lists "Boeye Redevelopment" at $259,949 in fiscal year 2024-25 and an estimated $162,139 in fiscal year 2025-26.
Combined, that is roughly $8.3 million in documented actual and estimated spending on Boeye.
So the "millions" are real. But most of the $21 million was not spent on the reservoir.
Boeye Reservoir McAllen: where the rest went
The $7.5 million.
On Nov. 10, 2025, four weeks after the Boeye press conference, the City Commission unanimously approved a $7.5 million budget amendment "between the Reservoir Development Fund and General Fund for the Ederra, LLC Property," according to the meeting's agenda packet and minutes.
A memo from the City Attorney's Office in the packet explains it. The city had filed an eminent domain case to acquire land for the Parks and Recreation Department, bordering Lark Avenue between 23rd and 29th streets. After a Sept. 3, 2025 hearing, special commissioners awarded $7,500,000. The budget amendment let the city deposit that award with the court, which gave the city the right to take possession.
The amendment form shows the Reservoir Development line dropping from $16,000,000 to $8,500,000, and the money landing in a General Fund account labeled "Extraordinary Item/Settlement."
The Monitor reported in July 2026 that the city acquired the land north of the Lark Community Center through condemnation for $7.5 million from Florida-based Ederra LLC, for a planned park. The owner is contesting the award, and a jury will decide whether the land is worth more or less than what the city paid, the paper reported.
The city's fiscal year 2026-27 budget document matches. It shows a $7,500,000 transfer out of the reservoir fund to the General Fund in fiscal year 2025-26, and a $7,500,000 General Fund expense labeled "Extraordinary Item."
The $6.56 million.
The same budget document shows a $6,561,289 transfer from the reservoir fund to the Quinta Mazatlán Center for Urban Ecology Fund in fiscal year 2026-27. That fund pays for the Center for Urban Ecology facility at Quinta Mazatlán. The document estimates the fund will end fiscal year 2025-26 at negative $14,967,646. Its 2025-26 budget had counted on $21,293,057 from the University of Texas Rio Grande Valley, a line the city's estimate shows as zero. With the Boeye money and other transfers, the fund is projected to end 2026-27 at $93,741.

The $2.6 million.
Another $2,597,600 is budgeted for City Hall expansion design, moved from the Development Corporation fund's budget. That one fits the fund's stated purpose.

The zero.
For fiscal year 2026-27, the department asked for $7,577,288 for Reservoir Development. That is exactly the amount left from the prior year's adjusted budget after the city's estimated spending. The City Manager's recommendation was zero. The City Commission's recommendation was zero. The Boeye line in the TIRZ 2A fund is also zero.
The fund's projected ending balance is zero.
The fiscal year 2026-27 pages reviewed for this report show no transfer putting the $7.5 million back into the reservoir fund.
A note on the document. Its cover is titled "Proposed" and dated Sept. 28, 2026, and its fund pages are dated Sept. 14, 2026. The city posted it under a file name identifying it as the approved budget. The McAllen News Tribune reported the commission adopted a $647 million budget by unanimous vote on Sept. 28, and Ordinance 2026-89 adopted it with amendments that The 956 Report could not match to the Boeye figures.
What that does and does not mean
A zero in a budget line does not mean a project has been stopped. The records reviewed show no decision to end the Boeye project.
There are ordinary explanations. A master developer could be expected to pay for infrastructure. Tawil told The Monitor the site sits inside a tax reinvestment zone, which lets growth in property tax value be put back into the development. The commission can amend a budget midyear.
Moving money between funds is also routine and legal. A park and a nature center are public projects. The $7.5 million move was approved in a public meeting. Nothing in these records shows any transfer was improper.
Tawil has argued the money already spent at Boeye was not wasted. He told The Monitor that back-filling the reservoir and stabilizing the ground created significant value in the real estate, and that the fill came from a regional detention facility that provided drainage relief to the Balboa area. "So those funds served two purposes," he said.
But the record does show this much. The city put $21 million into a fund for Boeye. It has spent a little more than a third of that, about $7.87 million, on the site, counting one year of city estimates. It used $7.5 million of the fund to pay a court award for park land. And the budget for the coming year sends what is left to other projects.
Nearly two decades of plans
This is not the first Boeye plan. The Progress Times has documented the history.

2007. McAllen hired Henry S. Miller Sustainable Partners to draft a master plan with a museum, a performing arts center and a birding pavilion.
2011. The city ended that agreement after paying the firm $275,000. Months later, it asked for new proposals and got one. According to the Progress Times, it was a proposal submitted by then-Mayor Richard Cortez's sons and business associates. Cortez recused himself. The commission rejected the proposal.
2013. The city dedicated a $14 million replacement reservoir south of the airport.
2019. Commission members traveled to Epperson, Florida, to see a community built around a man-made lagoon. Records released under the Texas Public Information Act labeled the trip "Project Blue Tour Site," the Progress Times reported.
2022. The commission met in closed session for about an hour and 40 minutes on Boeye. The fiscal year 2022-23 budget listed a total project cost of $26.4 million.
December 2022. The city set aside $450,000 for a feasibility study.
April 2024. KRGV reported the reservoir had been emptied. "It's a very valuable site, it's hard to find 70 acres on the expressway," then-City Manager Roy Rodriguez told the station.
July 2025. The city issued a request for statements of qualifications for a master developer. Responses were due Aug. 14, 2025.
October 2025. The city issued a request for proposals. Proposals were due Dec. 15, 2025.
November 2025. The city held a pre-submittal conference on Nov. 3. The Monitor reported that city staff would grade and rank proposals, then seek the commission's authority to negotiate with the top-ranked bidder. A week later, on Nov. 10, the commission moved $7.5 million out of the reservoir line.
January 2026. ValleyCentral reported the city had received only two bids, fewer than expected. Tawil said the project could be presented to the City Commission at its Jan. 12 or Jan. 26 meeting.
March 2026. On a March 18 episode of the Rio Grande Valley Business Journal podcast, Tawil said the city was negotiating with a developer, who was refining a proposal to present to the commission. He did not name the developer.

That is where the public trail on a developer goes quiet. City Commission agendas posted from December 2025 through November 2026 show no public item naming the Boeye development or a master developer, other than a Dec. 8, 2025 workshop update on the "Balboa RDF / Boeye Drainage Project." The commission does meet regularly in executive session on economic development matters that its agendas do not name.
The questions
The Texas Open Meetings Act allows economic development negotiations to be discussed behind closed doors. That is legal. It also means residents are left to read the budget.
So here are the questions the budget raises.
Who submitted the two proposals the city received on Dec. 15, 2025?
Which developer is the city negotiating with, and has the commission formally authorized those negotiations?
Will the $7.5 million used for the park land be returned to the reservoir fund? If so, when, and from where?
Why did the Reservoir Development request of $7.58 million come back at zero?
Were platting and infrastructure finished by September 2026, as the annual financial report said they would be?
If a developer is chosen, what does the city put in, and what does it get back?
That last question matters most. McAllen owns 70 acres on the expressway. Whoever ends up building on it, the public paid to drain it and fill it. The terms of the deal are the story. So far, there are no public terms to read.
What we couldn't confirm
The 956 Report could not confirm from the city's written meeting records whether officials stated a plan to repay the reservoir fund for the $7.5 million. The agenda packet and minutes for the Nov. 10, 2025 meeting do not mention one, and the 2026-27 budget shows no transfer back.
We could not confirm the outcome of Ederra LLC's challenge to the $7.5 million award. A jury could set the final price higher or lower.
We could not confirm whether the amendments the City Commission made when it adopted the 2026-27 budget changed any Boeye figure, because the posted document still carries the "Proposed" cover.
We could not confirm whether platting and infrastructure were completed by September 2026.
We could not confirm the names of the two bidders or of the developer Tawil said the city was negotiating with. No public announcement of a master developer turned up in a search of city postings and local news coverage as of Nov. 27, 2026.
Fiscal year 2025-26 figures are city estimates, not audited actuals, and may change when audited.
How this was reported
This report is based on City of McAllen budget documents for fiscal years 2023-24 through 2026-27, the city's Annual Comprehensive Financial Reports for fiscal years 2024 and 2025, the agenda packet and minutes of the Nov. 10, 2025 City Commission meeting, Ordinance 2026-89, City Commission agendas, public bid notices, and published reporting by the Progress Times, The Monitor, KRGV, ValleyCentral, the Rio Grande Guardian, the RGV Business Journal and the McAllen News Tribune. Figures labeled "estimated" are the city's own estimates and may change when audited.