Donna City Council Approves Nearly $7 Million in Bonds, Fraud Plan and Comp Time Caps

DONNA, Texas - The Donna City Council on Nov. 18, 2026, approved the sale of about $5 million in certificates of obligation and about $1.7 million in refunding bonds, after the city's financial advisor reported that both deals priced at lower interest costs than the city had projected.
At the same special meeting, the council adopted a fraud response plan that city staff tied to findings in the city's last audit, put caps on how much compensatory time employees can build up, and approved a work agreement with the Donna Economic Development Corporation (EDC) to build a detention pond at the Shops at 493.
All items passed without opposition heard. The 956 Report reviewed the city's meeting video, the posted agenda and the city's published bond notice. Items that could not be confirmed are noted below.
Video: City of Donna, Special City Council Meeting, Wednesday, Nov. 18, 2026, 5:30 p.m., at Donna City Hall, 307 S. 12th St. All council members were present. No one signed up for citizen participation.
DONNA CITY COUNCIL SELLS BONDS AT LOWER RATES THAN EXPECTED
What it means for you: The city is borrowing money for new equipment, fire station work, a fire truck, City Hall improvements and drainage, and refinancing older debt. The lower rates mean less interest paid over the life of the debt.
The council approved Ordinance 2026-21, issuing about $5 million in Combination Tax and Revenue Certificates of Obligation, Series 2026, to be paid off over 20 years. The city's financial advisor said the true interest cost came in at 4.697%, below the 5.039% the city had planned for.
"So, you're coming out better by not paying as much interest as we thought," the financial advisor told the council.
The council also approved Ordinance 2026-20, issuing about $1.7 million in General Obligation Refunding Bonds, Series 2026, to refinance existing debt over 10 years. The advisor said that deal came in at a true interest cost of 4.01%, compared with about 4.6% expected.
The underwriter is RBC Capital Markets. Winstead is bond counsel and McCall, Parkhurst & Horton is underwriter's counsel. Closing was set for Dec. 16, the advisor said.
The city's published notice of intention, signed by Mayor David Moreno, set a limit of $5.3 million for the certificates, with a final maturity no later than Feb. 15, 2046. It lists these planned uses:
Information technology equipment and city vehicles
Park equipment and lighting
Fire station renovations, including a fire truck
City Hall improvements
Drainage improvements
The notice listed $39,732,163 in outstanding principal on the city's existing tax-supported debt.

Ahead of the sale, S&P Global Ratings on Nov. 4 assigned an 'A' rating to the certificates and the refunding bonds. S&P set the outlook at negative, citing reserves that have declined over three years and stress on the city's water fund, which reported a negative unrestricted net position in fiscal years 2024 and 2025.
AEP TEXAS CASE AND HIGHWAY 68 LAND ON CONSENT AGENDA
The council approved its consent agenda in one vote. It included:
Resolution 2026-36, authorizing Donna to take part with other cities in matters involving AEP Texas and to hire legal counsel. Asked about it, the city manager said an outside firm already representing other cities in litigation had contacted Donna. "No risk to the city," he said, adding there would be no direct cost to the city.
A right-of-way deed to the Texas Department of Transportation for the International Bridge Trade Corridor / State Highway 68 project.
An item on a consultant for the city's international bridge was removed from the agenda.
FRAUD RESPONSE PLAN TIED TO AUDIT FINDINGS
What it means for you: Donna will have a written process, a hotline and staff training for reporting and handling suspected fraud involving public money.
The council approved Resolution 2026-37, adopting a Fraud Response Plan. A city finance official told the council the plan responds to the city's 2024-25 audit, which listed material weaknesses in the city's processes, about six to eight items. He said the Texas Water Development Board and the bond process had both asked what the city is doing to address them.
The plan defines fraud broadly. "Fraud commonly includes activities such as theft, corruption, conspiracy, embezzlement, deception, bribery, and extortion," the official read from the document.
Staff said a hotline is being set up, department directors will sign certifications, and training will start at a directors' meeting and move down through each department. The plan was reviewed by the city's legal counsel, staff said. No specific case of fraud was discussed at the meeting.
DONNA CAPS COMP TIME FOR CITY EMPLOYEES
The council approved Resolution 2026-38, setting limits on compensatory time. For regular employees, the cap discussed was 40 hours of overtime worked, which equals 60 hours of comp time. Time not used by the end of the year will be paid out, and use will be tracked every quarter.
Staff said comp time had kept building up in past years, "which created a huge liability for the city." Directors will be responsible for managing it with the city manager's approval.

SHOPS AT 493 DETENTION POND PROJECT
What it means for you: City crews will build a detention pond at the Shops at 493 to open land for commercial development, with the Donna EDC paying the cost.
The council approved a work authorization agreement between the city and the Donna EDC (4A) for the detention pond at the Shops at 493. An EDC representative said the project would cost roughly $360,000, including engineering by S2 Engineering, and that the EDC would pay for labor, materials and construction while city Public Works does the work.
The EDC got three quotes, and the city's came in lowest, the representative said, putting the savings at roughly $200,000 to $250,000. Work is scheduled to start at the end of January and finish toward the end of April. The project was discussed earlier in closed session under the names Project Green and Project Pond.
CITY MANAGER CONTRACT
The council met in closed session from about 5:56 p.m. to about 6:13 p.m. When it returned, it approved the terms of employment for City Manager Dr. Jesús René Reyna "as discussed" in closed session. The terms were not read aloud.

NEXT MEETING: WHAT'S ON THE AGENDA
No next Donna City Council meeting had been posted as of Nov. 21. Check the city's Agenda Center: https://www.cityofdonna.org/AgendaCenter/City-Council-7
WHAT WE COULDN'T CONFIRM
Votes were by voice. Who made and seconded each motion, and each member's vote, could not be confirmed. No opposition was heard.
The full name and title of the EDC representative and of the finance official who presented the fraud plan were not confirmed.
The comp time cap for public safety employees was not clearly stated at the meeting and is not included.
The terms of the city manager's employment were not disclosed.
SOURCES
City of Donna, Special City Council Meeting, Nov. 18, 2026 (meeting video)
City of Donna, Special City Council Meeting Agenda, Nov. 18, 2026
City of Donna, Notice of Intention to Issue Certificates of Obligation, Series 2026
S&P Global Ratings, Donna, Texas rating report, Nov. 4, 2026