Laguna Vista Town Council Learns Drainage Project Is Now Due in March 2027, Approves $75-an-Hour Accounting Contract

3 days ago
6 min read
Laguna Vista Town Council members seated at the council table beside a U.S. flag during the Nov. 17, 2026 regular meeting.
Laguna Vista Town Council regular meeting, Nov. 17, 2026. Frame from the Town of Laguna Vista's public meeting video.

LAGUNA VISTA, Texas - The Laguna Vista Town Council was told Tuesday night, Nov. 17, 2026, that a drainage project scheduled to finish in October has been extended to March 2027. Staff said $472,000 has been spent so far, most of it on engineering, with more than half of the money still available.


Need to know

  • Laguna Vista staff told the Town Council on Nov. 17 that a drainage project scheduled to finish in October has been extended to March 2027.

  • Staff said $472,000 has been spent so far, most of it on engineering, with more than half of the money still available; the council also approved a $75-an-hour accounting contract.

  • The drainage work is now scheduled to finish in March 2027.


In a short regular meeting, the council also approved a professional accounting contract at $75 an hour after a member asked for the contractor's resume, agreed to join a state program for turning in unwanted boats and changed a director's job title. It then went into executive session at 6:27 p.m.


The 956 Report reviewed the town's meeting video and posted agenda. The recording's automatic captions are rough in places, so names and votes that could not be clearly heard are not reported. Watch the full meeting below.



Video: Town of Laguna Vista, Town Council Regular Meeting, Nov. 17, 2026 (about 29 minutes).


THE MEETING


The council met at 6 p.m. at Town Hall, 122 Fernandez Street. Mayor Michael "Mike" Carter presided. The official roster is Frank Galvan, Place 1; Johvonne Hernandez Howard, Place 2; Norma Parker, Place 3; Kenneth Cornelius, Place 4; Teresa Bryant, Place 5; and Mike Hernandez, Place 6, mayor pro tem.


The mayor asked for a moment of silence for two local residents who had died in the previous week. No one spoke in the open forum. The council approved minutes from the Oct. 13 and Oct. 27 regular meetings.


DRAINAGE: WHAT THE LAGUNA VISTA TOWN COUNCIL HEARD


The drainage work is funded through the Texas General Land Office and Community Development Block Grant programs. Staff said the project "continues to have some struggles," especially with rain. It had been set to end in October. Staff said the town has been told verbally that it has been extended to March of next year, "plenty of time to complete that," and that the first phase must be completed no later than March 2027.


A council member said people have asked "where's the money go?" The member said $472,000 has been spent so far, "the majority of that is engineering," with "over half the money left to finish the project," and that the project is under budget. The member explained these are reimbursement grants: the town spends the money, then requests repayment for approved work. Staff agreed.


Staff said current work runs from Hibiscus, 1,300 feet north on Palm, and on Orange, Ebony and Mesquite. A separate grant application, already approved, would fund a next phase next year, finishing Mesquite and continuing to 510 and down to Fernandez. The town also submitted a pre-application to the General Land Office for a later third phase. Staff said a house-to-house income survey found 66 percent of residents in that area, and as much as 70 percent on some streets, meet the low-to-moderate-income test; the programs require at least 51 percent. Formal funding for that phase would likely be "two years down the road at least," staff said.


What it means for you: If you live along the streets in the current project area, expect construction to continue into early 2027. Residents on Mesquite and toward 510 and Fernandez are in line for the next phase.


OTHER PROJECTS: FIRE STATION, PARK AND CITY HALL


Laguna Vista Town Council members at the council table during staff project updates on Nov. 17, 2026.
Laguna Vista Town Council, Nov. 17, 2026. Frame from the Town of Laguna Vista's public meeting video.

  • Fire station expansion: Staff and the project architect said contractors are on site digging footings after rain delayed the start. The prefabricated building is supposed to arrive in 10 to 14 days, with substantial completion before Christmas and close-out in the first week of January. A council member said, "We need it done by December 31st," noting the remaining money is "the final $197,000 of COVID money." The 956 Report has not yet confirmed that figure in town records.

  • Roloff Park: Rain delayed finishing work on a soccer field but helped the grass come in. The contractor still has electrical items and grading to finish.

  • City Hall expansion: Staff said it had been "going pretty good" before the rain.

  • Comprehensive plan: Consultants wanted to start public meetings in December, but council members preferred January so more residents would be in town after the holidays. Staff said about six public meetings are expected over a project lasting about a year and a half.


THE ACCOUNTING CONTRACT


The Laguna Vista Town Council approved a contract for professional accounting services at $75 an hour, which staff said is the same as the prior arrangement. The contractor, identified in the meeting only as Irene, would have system access, work mostly remotely and come in as needed, billing for time the way the town's attorney does.


A council member said the town has been using her but asked whether a resume or other qualifications were available. Staff said a resume could be provided but was not in the room, and described her as an accounting graduate. The member also asked whether work in the scope of services, including monthly financial statements and budget-to-actual reports, should be done by the city manager or existing staff. Staff said the work is accounting, not preparing a new budget. The member then said, "If we can get that resume later on just to verify your qualifications. I'm good with it."


The contract was approved. The captions do not clearly record every council member's vote.


A BOAT TURN-IN, A NEW TITLE, AND A CLOSED SESSION


  • Vessel Turn-In Project: The council approved joining the program sponsored by the Texas Parks and Wildlife Department and the General Land Office, which helps people dispose of unwanted boats. A drop-off site has not been chosen. Staff said disposal costs would be covered by the agencies; liability and hauling details still have to be planned.

  • New job title: The council approved changing the Community Services Director's title to planning and development director. Staff said the employee had requested the change and that "planning and development is the correct term" for the work.

  • Executive session: At 6:27 p.m., the council voted to go into closed session under the Texas Open Meetings Act sections for legal advice, real property, personnel and economic development negotiations. As the item was read, a speaker said, "Want to go talk about the city manager." When the recording resumes, a motion is made to "proceed as discussed in executive session." The captions then become incomplete, and the posted video does not clearly show what, if any, action followed. Texas law requires final action in open session; the town's minutes should show any action taken.


WHAT TO WATCH


  • The Laguna Vista Town Council's official minutes of the Nov. 17 meeting, which should state any action after the closed session.

  • The accountant's resume, which a council member asked to see.

  • Whether the drainage project stays on track for its March 2027 deadline.


NEXT MEETING: WHAT'S ON THE AGENDA


The council meets next on Tuesday, Nov. 24, 2026, at 6 p.m. at Town Hall, 122 Fernandez St., according to the posted agenda. The main items: a contract for emergency medical services with Los Fresnos Ambulance Service, Inc.; amended general policies for the police department; and the town's financial report for the period ending Oct. 31. The council is also scheduled to go into closed session on the city manager and then consider hiring an executive search firm. Agenda items can change before or during a meeting.


WHAT WE COULDN'T CONFIRM


  • Roll-call votes. The full roll call was not clearly audible on the video for the accounting contract, the boat program or the job title change, so we have not reported how each member voted or called any vote unanimous. We also could not confirm from the video whether every listed council member was present.

  • Fire station funding. The $197,000 figure and its description as the town's last COVID relief (ARPA) money come from a council member's remarks. We have not yet confirmed the amount in town records.

  • Closed session. The posted video does not clearly show what, if any, action followed the executive session. We will update this story when the town posts the official minutes.

  • Names. The accounting contractor was identified in the meeting only by her first name, and the employee whose title changed was not clearly named, so neither is identified here.

  • Grant figure. A grant amount mentioned near the end of the comprehensive plan discussion could not be matched to a specific project from the video, so it is not reported.


SOURCES


Town of Laguna Vista, Town Council Regular Meeting, Nov. 17, 2026 (video):


Town of Laguna Vista, agendas and minutes:


Town of Laguna Vista, Town Council Members:


Texas Government Code Chapter 551 (Open Meetings Act):


Images: frames from the Town of Laguna Vista's public meeting video, credited to the Town of Laguna Vista.


Comments


bottom of page