NextDecade Wants Two More LNG Trains in Brownsville. The Valley's Biggest Gas Project Is Not Done Growing.

1 day ago
6 min read

Five liquefaction trains are under construction on the Brownsville Ship Channel. A sixth is in federal review. Now the paperwork has started on a seventh and an eighth.


Slide titled Rio Grande LNG Expansion Project with text about Train 6, a marine jetty, and Brownsville Ship Channel in Texas.

A NextDecade affiliate called RG2 LNG made a filing with the Federal Energy Regulatory Commission on November 11, 2026, for a project labeled the RG2 LNG Terminal, according to a project-tracking alert reviewed by The 956 Report. The alert describes two liquefaction trains with a combined capacity of up to 12 million metric tons of LNG per year and an expected completion date of 2033.


Those numbers match what NextDecade has already told its investors. In its third quarter update on October 29, the Houston company said it is developing Trains 7 and 8 on the western end of its Rio Grande LNG site and expected to start the FERC process for them before the end of 2026. The company has put the combined capacity of those two trains at about 12 million tonnes per year.


WHAT IS CONFIRMED AND WHAT IS NOT


The 956 Report was not able to locate the November 11 filing itself in public search results as of publication. The FERC public page for Brownsville projects did not yet list an RG2 entry or a docket number. The filing date, the RG2 LNG name and the 2033 completion date come from the alert, not from a document The 956 Report has read.


One distinction matters. The alert describes the filing as an application seeking approval to construct. NextDecade's own words on October 29 were that it expected to "pre-file" for Trains 7 and 8. Those are different steps.


Pre-filing is the front end of the FERC process for LNG terminals. It opens a docket, starts environmental scoping and brings in public comment before a formal application is filed. FERC rules require LNG terminal developers to spend at least six months in pre-filing first.


Train 6 followed that path. The request to begin pre-filing went in on November 21, 2025. FERC accepted it on December 22, 2025. The formal application followed on May 26, 2026.


Analysis: Given the company's stated plan thirteen days earlier and the six-month rule, the November 11 filing is most likely the opening of pre-filing review, not a final application to build. If that is correct, a formal application would be expected around mid-2027, and a FERC decision would come after that. That reading is this publication's analysis, not a confirmed fact.


IS IT A NEW TERMINAL?


The alert calls RG2 a new gas export terminal. The public record points to the same ground. NextDecade has said Trains 7 and 8 would sit on the western end of the existing Rio Grande LNG site at the Port of Brownsville. On its October earnings call, the company described the two trains as a single standalone project running about a year behind Train 6.


The separate name fits a pattern. Each phase of Rio Grande LNG has its own legal entity. Train 6 is being permitted by Rio Grande LNG Train 6, LLC. A separate company name does not by itself mean a separate location.


One site detail is worth watching. In February 2025, NextDecade said Trains 7 and 8 were being developed outside the existing levee at the site. Train 6 is inside it.


Satellite project overview map of Cameron County, Texas, showing terminal, dredged area, and permanent laydown area along SH-48.
Industrial site plan for RG2 LNG in Brownsville, Texas, showing berths, train units, tanks, haul road, turning basin, and labels

THE SCALE


Here is where Rio Grande LNG stands, using NextDecade's own filings.


Trains 1 through 5 are under construction. In September 2026, FERC raised their authorized capacity to 30.15 million tonnes per year, up from 27 million.


Trains 1 and 2 were 79.7 percent complete as of September. Train 3 was 55.2 percent. Train 4 was 22.5 percent. Train 5 was 14 percent.


First LNG from Train 1 is expected in the second quarter of 2027. First gas into the plant is expected before the end of this year.


Train 6 would add about 6 million tonnes. FERC's final environmental impact statement is scheduled for June 25, 2027. The U.S. Army Corps of Engineers issued its permit authorization in September 2026. NextDecade is targeting a final investment decision in the second half of 2027.


Trains 7 and 8 would add about 12 million more. That brings the total under construction or in development to roughly 48 million tonnes per year.


The company says the site has room for 10 trains. It has said potential Trains 9 and 10 would go on the eastern side.



WHAT STANDS BETWEEN A FILING AND A PLANT


A FERC filing is not a construction start. NextDecade's own disclosures say expansion trains depend on government approvals, signed sales contracts, financing and a final investment decision. None of those are in place for Trains 7 and 8.


The first five trains show how long the road can run. FERC first approved Rio Grande LNG in November 2019. Court challenges followed. The D.C. Circuit vacated the reauthorization in August 2024 in a case brought by parties including the City of Port Isabel, then revised that ruling in March 2025 to leave the approval in place during further review. FERC reaffirmed the project in August 2025. In May 2026, FERC gave the company until November 22, 2031 to finish all five trains.


Opposition has not gone away. The Sierra Club, the South Texas Environmental Justice Network and Border Workers United filed a protest in August 2026 against the Train 6 export application at the Department of Energy. NextDecade's affiliate filed an answer opposing that protest in September. When FERC reviewed the capacity increase for Trains 1 through 5, it logged comments from the City of Port Isabel, the Carrizo/Comecrudo Tribe of Texas, those same groups and about 114 individuals.


FERC's own 2025 supplemental review of the first five trains concluded overall impacts would be less than significant, while also finding that impacts on nearby environmental justice communities would be disproportionate and adverse.


THE OTHER PROJECT DOWN THE CHANNEL


Rio Grande LNG is not the only export project on the ship channel. Texas LNG, a 4 million tonne per year project owned by Glenfarne, has not started full construction. On September 28, 2026, it asked the Department of Energy to push its deadline to begin exports from February 10, 2027 to February 10, 2032, citing six years of litigation.


One developer is asking for five more years to start. The other is filing for trains seven and eight.


QUESTIONS THE RECORD DOES NOT YET ANSWER


What exactly did RG2 LNG file on November 11, and under what docket number?


Where on the western end of the site would the two trains sit, and how much of that footprint is outside the existing levee?


Would Trains 7 and 8 need new storage tanks, a new berth, or more pipeline capacity than what is already approved?


How many more LNG carriers would move through the Brownsville Ship Channel each week at 48 million tonnes per year?


Will FERC review Trains 6, 7 and 8 together for cumulative air and community impacts, or one project at a time?


When and where will public scoping meetings be held for Valley residents?


The answers will sit in the FERC docket once it is public. The 956 Report will report on that record when it is available.



------------------------------------------------------------

PUBLISHING AND SEO PACKAGE

------------------------------------------------------------


Blog headline:

NextDecade Wants Two More LNG Trains in Brownsville. The Valley's Biggest Gas Project Is Not Done Growing.


SEO title tag (54 characters):

NextDecade Files for Trains 7 and 8 at Brownsville LNG


Meta description (153 characters):

A NextDecade affiliate, RG2 LNG, has filed with FERC for two more LNG trains in Brownsville. Here is what the record confirms, what it does not, and why.


URL slug:

nextdecade-rg2-lng-trains-7-8-brownsville-ferc-filing


Excerpt:

A NextDecade affiliate has started the federal process for two more LNG trains at the Port of Brownsville. The filing would push the Rio Grande LNG complex toward 48 million tonnes a year, but it is a first step, not an approval.


Focus keywords:

Primary: NextDecade RG2 LNG, Rio Grande LNG Trains 7 and 8, Brownsville LNG terminal

Secondary: FERC pre-filing, Port of Brownsville, Rio Grande LNG expansion, Train 6, Texas LNG, Port Isabel, LNG exports Rio Grande Valley



------------------------------------------------------------

LEGAL AND ACCURACY NOTES (NOT FOR PUBLICATION)

------------------------------------------------------------


1. The November 11 filing, the RG2 LNG name and the 2033 date rest on the alert alone. The article says so. Do not upgrade these to confirmed fact in the headline, reel or teleprompter script until the FERC docket is in hand.


2. Do not call the filing an "application to construct" or say NextDecade "will build" a new terminal. The company's last public statement was that it would pre-file. The article labels the pre-filing reading as analysis.


3. Do not call it a "new terminal" without the qualifier that company statements place Trains 7 and 8 on the existing Rio Grande LNG site.


4. Date discrepancy on Train 6 pre-filing: NextDecade's Q4 2025 update says it initiated pre-filing on November 4, 2025. FERC's project page and NextDecade's Train 6 page give November 21, 2025 for the request. The article uses the FERC date.


5. No health or harm claims are made. The only impact language is FERC's own finding from its 2025 supplemental review.


6. No defamation or Texas Penal Code 42.06 exposure identified. All statements about the company trace to its own releases, federal dockets or the attributed alert.