top of page

The Valley Is Not Waiting on Elon Musk: The Numbers Behind a Region Already in Motion

3 days ago
6 min read

Three votes. That is all it took on Tuesday for Cameron County to stop SpaceX's request for a 10-year, 100 percent property tax abatement on a $24 billion data center and natural gas power plant.


Need to know

  • Cameron County stopped SpaceX's request for a 10-year, 100 percent property tax abatement on a $24 billion data center and natural gas power plant.

  • The request was for a 10-year, 100 percent abatement on that $24 billion project.

  • Port, bridge and project records cited in the article show the Valley was already being built for industry before the vote.


By Wednesday, a post promoting Thursday's edition of The Sergio show on KURV was asking the question a lot of people are asking. If Elon Musk packs up and leaves, taking future well-paying jobs with him, what jobs will the politicians provide?


It is a fair question. It also sells this region short.


The record shows the Rio Grande Valley was already being built for industry before this vote, and it is still being built for industry after it. Here is what is confirmed, what is reported, and what is my own read.


The Starbase sign and rocket production buildings with construction cranes along State Highway 4 at Boca Chica, Texas
Starbase at Boca Chica, Cameron County, June 2021. Photo: Alexander Hatley, CC BY 2.0, via Wikimedia Commons.

WHAT THE COUNTY ACTUALLY VOTED ON


On Nov. 17, the Cameron County Commissioners Court voted 3-2 against setting a public hearing on the SpaceX abatement request.


County Judge Eddie Trevino Jr. and Precinct 2 Commissioner Joey Lopez voted to move it forward. Precinct 1 Commissioner Sofia Benavidez, Precinct 3 Commissioner David Garza and Precinct 4 Commissioner Gus Ruiz voted no.


The vote was not on the tax break itself. It was on whether to hold the hearing where the final numbers would have been presented. Lopez told KRGV he wanted to see all the facts and figures first, and that without a second meeting the request is dead.


According to KRGV, the SpaceX application listed a $24 billion capital investment, $13.8 billion in taxable value in the first year, and 500 new jobs. A $26 billion figure has circulated, including from a speaker at the meeting. The figure reported from the application is $24 billion.


WHAT SPACEX HAS AND HAS NOT SAID


SpaceX has not announced that it is leaving Cameron County.


What the Brownsville Herald reported is narrower. In its abatement application, the company said that without the tax break it would "redirect current and/or future investment to other super compute facility sites outside Cameron County." In the same application, SpaceX said initial construction has already started, the Herald reported.


On Wednesday, SpaceX posted a defense of the proposal on X. The company said the deal was built around payments in lieu of taxes that would have given the county predictable revenue as expensive computing equipment loses value.




Two other facts belong next to that. The Texas Commission on Environmental Quality issued an air permit for the data center and power plant site on Monday, one day before the county vote, the Herald reported. And the City of Starbase has its own hearing on a separate SpaceX abatement set for Dec. 9.


So the record shows a warning about where future computing dollars could go. It does not show a company closing a launch site where it says it has already invested more than $15 billion.


THE PORT: 13.9 MILLION TONS TO 28 MILLION IN FOUR YEARS


Now look past Starbase.


The Port of Brownsville moved 28 million tons of cargo in fiscal year 2025. That matched the record set the year before. In 2021 the number was 13.9 million tons. The port calls that growth of more than 101 percent.


The ship channel project is finished. Seventeen miles deepened to 52 feet, at a cost the port puts at more than $500 million, through a partnership of the U.S. Army Corps of Engineers, the port and NextDecade.


A crane on a barge places stone along the jetty at the entrance to the Brownsville Ship Channel on South Padre Island
Jetty repair work at the entrance to the Brownsville Ship Channel, May 2013. Photo: U.S. Army Corps of Engineers, Galveston District (public domain), via Wikimedia Commons.

At its State of the Port address in June, the port listed what is lined up along that channel:


Rio Grande LNG. A $36 billion investment on 984 leased acres. Five of eight trains under construction. Exports expected in 2027. The port says 73 percent of more than 5,000 on-site skilled workers are Valley residents.


America First Refining. Announced in March as the first new U.S. Gulf Coast refinery in nearly 50 years, designed to process up to 60 million barrels of domestic crude a year. BIC Magazine reported this month that civil site work has begun on a 240-acre site leased from the port, and that the company has hired Morgan Stanley to lead a $4 billion raise to build it. The money is still being raised.


Karpowership. A $3 billion investment after acquiring the AmFELS shipyard.


Forza Steel. More than $100 million in a 650,000-square-foot facility on State Highway 48, with more than 100 jobs.


Defense-related projects. About $14.5 billion combined, with what the port describes as potential for more than 20,000 jobs.


Power. The port is negotiating with Synergia on a proposed 1.5-gigawatt natural gas facility on about 350 acres.


The port puts its total project pipeline at more than $30 billion in potential investment.


Read those words carefully. "Pipeline" and "potential" are the port's terms. Announced is not built. Some of these projects will change, shrink or never happen. And the cargo number was flat last year, not up.


But none of that list depends on a county tax hearing for a data center.


THE BRIDGES: CAPACITY JUST DOUBLED


On Nov. 13, four days before the county vote, the Pharr International Bridge opened its twin bridge to traffic at full capacity. Bridge Director Luis Bazan told Texas Border Business the new structure is a 100 percent increase in capacity.


Trade through Pharr runs at roughly $50 billion a year and supports about 92,000 jobs, according to figures Bazan has cited from the state comptroller.


Twelve miles west, the Anzalduas International Bridge is finishing an $88 million expansion to carry fully loaded trucks in both directions. McAllen's bridge superintendent, Juan Olaguibel, said in May the project was 99 percent complete.


A Texas Department of Transportation study cited by the Rio Grande Guardian projects commercial truck traffic in the Valley and Tamaulipas border region could nearly triple by 2050.


In Pharr, Mexico Business News reported in August that the city is working a pipeline of nearly $1 billion in potential industrial investment, on top of more than $500 million in confirmed investment the Pharr EDC recorded in 2025.


MY READ


This part is analysis, not record.


Drive Highway 48. Drive Military Highway. Sit in the truck line at Pharr. The Valley is en chingas. Ports, bridges, warehouses and roads are being built for demand that is already here or already on its way.


The pull is not one company. It is location on the border, a deepwater port, land that costs less than the big Texas metros, and a workforce that is already filling the jobs. The LNG number says it plainly. Nearly three out of four workers on that site live here.


SpaceX is a big part of this story. The company told a state commission earlier this year that it has put more than $13 billion into the regional economy and that nearly all of its Starbase employees live in Cameron County, the Texas Tribune reported. If future computing investment goes somewhere else, that is a real loss and nobody should pretend otherwise.


But the people who filled the commissioners court on Tuesday were not arguing against industry. Speakers argued that abatements are meant to recruit companies that are not here yet, and that the county needs the tax dollars for roads and long-term water supply. Agree or disagree, that is a debate about terms. It is not a debate about whether industry is coming.


That is the shift. A region that used to take whatever deal it could get now has enough momentum to ask what it gets in return.


The hidden gem that was the Rio Grande Valley is not hidden anymore.


The question is no longer whether industry will come. The question is what the Valley asks for now that it has something everybody wants.